THANK YOU so much to the Stockdale Community for passing this bond that is going to make a huge impact on students for years to come.  As an update, substantial progress has been made so far on Bond Projects that were a result of the November election.  The following projects have been completed along with projected completion for the ongoing components of the projects:
 
  • 1) All 5 A/C units were installed on route buses over Spring Break.
  • 2) 54 additional interior/exterior cameras have been installed as outlined in a portion of the Safety & Security needs.
  • 3) Asbestos Abatement and Building Demolition was completed over Spring Break.
  • 4) Access door controls, district-wide are to be completed by end of June.
  • 5) Junior High Gym with Stage and Science Classrooms / Lab planning is still underway.  Construction is anticipated to take 10 months with a tentative move-in of July 2020.